April Progress

  • Demolished old KidsTown (“A” Wing)
  • Removed Foundation
  • Extensive Dirtwork
    • Dug 12 ft down
    • Filled 8 inches at a time
    • Packed & Treated each layer
    • Filled back up to the top

These are some of the businesses we are partnering with to Build the Future at Tabernacle.

Building the Future September Update

This is a BIG Update! We have so many exciting things to let you know about with our Building the Future progress. The new kidstown building is looking great, we have started demolition in the Welcome Hallway for improvements and new bathrooms, and we have started...

read more

Building the Future August Update

Construction If you have driven by the church in the past week or two, you might have seen some of the changes going on to the outside of the building, but the inside is coming along quickly. The roof is almost finished - There has been a structure there since May,...

read more

Building the Future – July Update

Construction In the month of July, we have made some major visible progress. The exterior framing has been completed, exterior walls have been built and the they have begun framing the interior, running HVAC and fire sprinkler systems. When you walk into the building,...

read more

Building the Future – June Update

Construction We are so excited about the progress that GPD has made with the construction Process. They have been great to work with. Despite a few weather delays, they are making excellent progress. On May 25th, they began pouring the foundation. On May 31st, the...

read more

Building the Future – May Update

The KidsTown building has much of the plumbing and electrical put in place as they prepare to pour the foundation. These are some of the businesses we are partnering with to Build the Future at Tabernacle.

read more